220kV line in Romania

First advanced reconductoring project in Romania, with an ACPR Losag conductor stranded by Nexans and installed by Electromontaj, using Tesmec machines and fittings from Dervaux (Sicame group).

For this project located in a challenging mountainous region, Transelectrica selected a 100% carbon fiber core encapsulated in aluminum to accomodate heavy ice loads during winter times.

Cristi OICA, Electromontaj site manager shared his experience on the conductor installation in the video below.

Year: 2024

Customer: TRANSELECTRICA

Location: Stejaru – Fantanele – Gheorgheni, Romania

Voltage: 220kV

Conductor length: 90km

Old Conductor: ACSR

New Conductor: ACPR Losag 8.5mm

Results:
– Doubled ampacity with existing structures
– Decreased line losses by up to 30%